Plot 24, Alexander Rd, Tygervalley, Shere, Pretoria-East
Mon - Thurs: 08-4:30, Fri: 08-4:00
012 809 8900

Flagstaff Square

Mike Buyskes Construction > Retail > Flagstaff Square

Project Detailsx

Project Overviewx

Start Date:October 2020
Project Completion Date:September 2021
Contract Value:R 105 million
Client:McCormick Property Development
Architect:MDS Architecture

Flagstaff Square was our first project in the Eastern Cape. Set in the foothill mountains between Kokstad and Lusisiki, it presented an opportunity to get back to work post Covid-19. We had to find our own water source through boreholes drilled on site due to a lack of adequate municipal water. We also set up the first commercial-scale concrete batch plant on the site for the project, which used 50 000 – 60 000 liters daily to cast concrete slabs. The centre has a GLA of 10 500 meters squared, double storey. Although the climate and rainfall had an impact, we completed the project on time.